Projects
Your experienced Partner in Offshore Wind
Thanks to the commitment of its experienced and qualified employees, OffShip GmbH can look back on a wide range of offshore wind projects in which it has successfully and decisively participated. A special focus and core competence lies in the commissioning management and quality assurance of offshore substations. However, TP projects in the construction and maintenance phase have also been guided by our employees in accordance with the interests of our customers to the desired result.
Get yourself an overview of our portfolio and experience!
Onshore projects
BorWin Gamma
Checking of Welding Instructions
Continuous checking of welding instructions of the steel structure and foundation structure of the BorWin Gamma as an independent inspector.
2016/17
Merkur
Project Status Controls
Inspections of the jacket structure and topside structure of the Merkur OSS at the Dutch and Belgian sites to ascertain the progress of the project.
06-08/2017
Merkur
Commissioning Engineer
Supervision and verification of the harbour acceptance tests (HAT) for the auxilary systems of the Merkur OSS at the Belgian site on behalf of the EPCI contractor.
09-12/2017
Merkur
As-Built Documentation Coordination
Coordination of the as-built documentation package of the Merkur OSS on behalf of the EPCI contractor.
2018
HornsRev 3
Project Status Controls
Inspections at the TPs at the Danish assembly site to ascertain the project progress.
05/2017
HoheSee/ Albatros Projekt
Commissioning Management
Coordination of the harbour acceptance tests (HAT) for the auxilary systems of the OTM Albatros at the Belgian site on behalf of the EPCI contractor.
01-03/2019
Moray East
Project Status Controls
Inspections on the WTG jacket foundation structures at the Belgian and the British site to ascertain the project progress.
01-02/2020
Moray East
Preparations for Commissioning
Creating checklists for harbour acceptance tests (HAT) of WTG jacket foundation structures.
03-05/2020
DanTysk & Sandbank
Project Engineer for Operation and Maintenance Processes of TPs & WTGs
General project management for operations and maintenance processes, coordination of subcontractors, planning and execution of offshore work and inspections, work preparation, tracking and documenting of the campaign status, processing and preparing maintenance schedules, clarification and follow-up of technical problems, budgeting and budget follow-up.
2021 – 2024
Adaptation of escape and rescue plans
Adaptation of escape and rescue plans of numerous ships with additional safety equipment after retrofitting ballast water treatment systems supported by a change log to compromise new plan approval by the class.
2022 – 2024
Offshore-Projekte
HoheSee/ Albatros Projekt
Offshore Commissioning Coordination in Rotation
Coordination of offshore commissioning works of OTM Albatros → management of PtW system, execution of TBTs, resources planning, subcontractor coordination, CTV coordination, logistics management, defects verification, etc.
04-12/2019
Amrumbank West
EoW-Inspection
EoW inspection of the Amrumbank West transformer platform (steel structure including diesel tank inspection, partial equipment components).
09/2020
Global Tech I
Periodic Inspections (PI)
Periodic inspections (PI) of the Global Tech I OSS (steel structure including void space inspection, partial equipment components).
10/2020
DanTysk
Coordination Offshore SOV WTG/ FOU Maintenance Campaign
Work scheduling, determining locations, subcontractor coordination, managing TBTs, daily reporting, CTV coordination, interface management, etc.
2021 – 2024
Projects before 2021 were accompanied in cooperation with other companies.